Kickoff meeting for the loader project in the Lvsi operation area of Qidong Port, Nantong Inland Port


Release time:

2022-08-26

On August 16, 2022, the kick-off meeting of the ship loader project in Lvsi operation area of Qidong Port, Nantong Inland River Port held in our company the project kick-off meeting of the "ship loader project of Phase I of Inland River Transfer Wharf in Lvsi operation area of Qidong Port, Nantong Inland River Port". Participants in this meeting were: the owner: Jiangsu Lvsi Port Group Co., Ltd., the supervisor: China Classification Society Industrial Co., Ltd., and the winning bidder: Jiangsu Sinomine Heavy Equipment Co., Ltd.

On August 16, 2022, the kick-off meeting of the ship loader project in Lvsi operation area of Qidong Port, Nantong Inland River Port held in our company the project kick-off meeting of the "ship loader project of Phase I of Inland River Transfer Wharf in Lvsi operation area of Qidong Port, Nantong Inland River Port". Participants in this meeting were: the owner: Jiangsu Lvsi Port Group Co., Ltd., the supervisor: China Classification Society Industrial Co., Ltd., and the winning bidder: Jiangsu Sinomine Heavy Equipment Co., Ltd.

 

1

 

This project is located in the Lvsi Operation Area of Qidong Port District, Nantong Neihe Port. To the east, it is adjacent to the Xigang Pool in the Lvsi Port Operation Area of Tongzhou Bay Port District, Nantong Port, and to the rear is Lvsigang Town, Qidong City. This project will build a new bulk cargo export berth on the north side of the port basin, mainly for loading mining and construction materials. The main materials for mining and construction are bulk materials such as yellow sand and stones, with an investment of 35 million yuan in this project.

Our company has won the bid for one 3000th rated arc track loader, belt conveyor, and auxiliary equipment. This project is a turnkey project for package installation.

Starting from August 1st, at the request of the owner, the supervising party conducted a survey on our company, including its scale, production equipment, inspection equipment, personnel configuration, installation team, installation qualifications, and other various software materials. The survey was highly recognized by the supervising company. At the kick-off meeting, all parties present discussed the "Construction Organization Design Plan" and "Engineering Division and Subdivision Table" submitted by our company We have reviewed the production and construction schedule and other materials, asked questions about various details, and received appreciation from the attendees. Our company stated that this project is tight in time and heavy in tasks. To ensure the smooth operation of the project, all departments of our company closely cooperate, arrange various work reasonably, overcome difficulties, and resolutely complete this project before the agreed delivery time in the contract.